So we had this boat ramp job set up for this other crew to do, they called the night before and said they couldn't do it. So our guys picked up the call and we rocked it out. Let's take a look...
http://picinfinity.co/d/6c93b53c-891d-410e-a6c4-51d1e245cc92.jpg
Looks like the cofferdam(giant blue bag of water) is already in place with the water pumped out so we have a Simi dry place to work, cool
And 12 hours later....
http://picinfinity.co/d/c5c0a701-2e45-4dcc-bdee-3ae7b7fc062c.jpg
Everything set up, the ramp will be 80ft long and 14ft wide.
The next day...
http://picinfinity.co/d/f7d46f0e-15fd-4592-a0f5-bb0b2b4860ce.jpg
We used a pump truck on this, thank God
http://picinfinity.co/d/4823b72f-a8a9-4ffe-951e-bfa7363057b0.jpg
All poured out with a tine rake finish